Bahrain LNG W.L.L. (BLNG)

Year of Establishment

2015

Shareholding

30% nogaholding
30% Teekay, Canada
24% GIC, Kuwait
16% Samsung C&T, South Korea

Business/Sector

Receiving terminal for regasification of Liquified Natural Gas (LNG)

Capacity

800 MMSCFD

Operational
Performance

Bahrain LNG construction commenced mid-Q4 2016 with GS Engineering & Construction (South Korea) as the main contractor  The majority of construction works were completed in 2018 and the project is now entering the Commissioning Phase.

At December 31st 2018:

  • The breakwater and piling construction works were completed offshore;
  • The offshore jacket structure fabricated in South Korea was transported to the offshore project site in Bahrain and permanently installed in Q2/18;
  • The Regasification Platform fabricated by CUEL in Thailand was transported and installed onto the offshore jacket in Q4/18;
  • The subsea and onshore pipeline has been installed, including the sections constructed by Horizontal Directional Drilling (HDD) by NSCC;
  • Offshore pipe racks and access trestles were fabricated by AMA in Bahrain and installed offshore;
  • Civil works on the Onshore Reception Facility (ORF) have been concluded;
  • Equipment for the Nitrogen Production Facility (NPF) has been delivered and installed;
  • The “Bahrain Spirit” FSU was delivered from DSME and was engaged in short term trading;


99%

The overall project design, engineering and construction progres

Operational
Performance